We thought it time to update everyone on the progress
on the repeater. As far as equipment goes,
everything is to plan, the repeater itself is built and tested and is
currently on soak test. It can be taken down to the site and installed
once the NOV has been received. The cavity / filter set is also ready,
we're trying to sort a convenient date for installing it at the site.
From previous updates, you'll know that the aerials are already up and
waiting. A 19 inch cabinet is already in place and will be used to house
the repeater.
As some may be aware, there have been changes in
the way that repeater applications are now handled. A new web site
exists that explains it all. It can be found at
http://www.ukrepeater.net
http://www.ukrepeater.net/vetting.htm tells us that our application
has cleared the RIS, and is now with NFAP. This should be the last
hurdle, and once we've cleared that, the NOV should follow shortly
after.
http://www.ukrepeater.net/gb3oa.htm is "our" page on the ukrepeater
site. Please take time to look through the ukrepeater.net site, it's
very informative.
|